The short answer
In Wales a garden room is permitted development under Class E of the 1995 Order, as substituted in 2013. No part may exceed 2.5 m within 2 m of a boundary, and no part may exceed 1.5 m within 2 m of the house. Otherwise the limits are 4 m for a roof with more than one pitch, 3 m for any other roof, and eaves of 2.5 m. A certificate of lawfulness for a proposed room costs £141.50.
A garden room in Wales is not covered by the same rules as one in England. The Order that gives the permission is the 1995 one, and its Class E was rewritten for Wales in 2013. The result looks familiar, with a 2.5 m limit near a boundary and a 4 m ridge, but three parts of it are different: heights are measured part by part, there is a 1.5 m limit next to the house, and a side wall facing a road brings a 5 m line into play. The free 3D check runs these Welsh tests for your own plot.
Which law applies in Wales
The permission comes from the Town and Country Planning (General Permitted Development) Order 1995, Schedule 2, Part 1, Class E. That Order no longer applies in England, but it still governs Wales. Class E as it now stands was substituted for Wales by SI 2013/1776 (W.177), which came into force on 30 September 2013. We read the revised text on legislation.gov.uk on 18 November 2026.
The class covers a building, enclosure, raised platform or pool required for a purpose incidental to the enjoyment of the house as such. A home office, gym or studio for the household is the usual example. Whether your use is incidental is a judgement your council makes, and the garden room use checker shows where the line usually sits.
Three limits sit outside the height rules. Paragraph E.1(d) allows one storey only. Paragraph E.1(b) bars any part from extending beyond a wall in the principal elevation of the original house, so the room sits behind the front of the house. Paragraph E.1(a) caps the ground covered by buildings, enclosures, raised platforms, pools and containers at 50% of the curtilage, leaving the original house out of the sum.
Check with your council
Wales has its own order
Do not read an English guide and assume it holds here. The Welsh text is a different Order with different paragraph numbers, which is why the check cites E.1(f) and E.1(h) for Wales.
Heights measured part by part
Welsh Class E measures height “from the surface of the ground immediately adjacent to that part” in E.1(e), and E.1(f) and E.1(h) use the same test, height above the ground immediately adjacent to the part concerned. A room on a slope is judged one part at a time, from the ground next to that part, not from one datum for the whole building.
2.5 m for parts within 2 m of a boundary
Paragraph E.1(f) rules out any part that is both within 2 m of the boundary of the curtilage and more than 2.5 m above the ground next to it. Because the test attaches to each part, a room with a low wall near the fence and a taller section further in can pass where a single tall box would not. On a slope the downhill side sits on lower ground, so the same wall measures taller there: measure at the ground next to each wall within 2 m of the boundary. The garden room height limits guide compares the sloping cases in all four nations.
1.5 m for parts within 2 m of the house
This limit has no counterpart in England’s Class E. Paragraph E.1(h) rules out any part of the building, enclosure, pool or container that is within 2 m of the dwellinghouse and more than 1.5 m above the ground immediately adjacent to it. A room placed 1.5 m from the back of the house can only have the strip nearest the house at 1.5 m or below. Moving the tall part of the room to 2 m from the house wall usually solves it.
4 m for a multi-pitch roof, 3 m otherwise, eaves at 2.5 m
Beyond those two zones, E.1(e) allows 4 m where the building has a roof with more than one pitch, such as a dual-pitched roof, and 3 m in any other case, which includes a flat or mono-pitch roof. Paragraph E.1(g) limits the eaves to 2.5 m at any point along their length. Paragraph E.5 explains the measurement: the eaves are where the external walls meet the lowest point of the upper surface of the roof, and a parapet wall or an overhanging part of the roof is left out. On a flat roof the eaves sit at roof level, so in practice a flat roof room is held near 2.5 m by the eaves limit.
The 5 m road rule
Paragraph E.1(c) deals with a side wall that faces a road. It rules out any part of the building that would extend beyond a wall in a side elevation of the house and be nearer to the highway than either the side wall nearest the highway or “any point 5 metres from the highway”, whichever is the nearer to the highway.
On our reading, the line that counts is the one nearer the road. If the side wall of the house is 8 m from the road, a room beyond that wall may come as close as 5 m. If the side wall is only 3 m from the road, the room may come no nearer than the wall itself. Paragraph E.4 says a part extends beyond a side wall if it is in front of that wall as it exists, or as it would be if extended to the boundary of the curtilage. This matters on corner plots and on houses whose side garden faces a street, and the check reports the line for your distances. Your council decides how the paragraph applies to your plot.
Conservation areas, National Parks and other designated land
Paragraph E.2 applies to “article 1(5) land” or a World Heritage Site. Part 2 of Schedule 1 lists article 1(5) land as National Parks, areas of outstanding natural beauty, conservation areas designated under the Historic Environment (Wales) Act 2023, the Broads and areas specified under section 41(3) of the Wildlife and Countryside Act 1981. On that land two extra limits apply:
- Buildings, enclosures, pools and containers more than 20 m from any wall of the house may cover no more than 10 m² in total.
- No part may stand on land between a side wall of the house and the section of the boundary that faces that wall.
In England the 20 m rule does not apply in conservation areas; in Wales it does. Ask your council whether your plot is on designated land before you rely on any map. A garden room is not permitted development in the curtilage of a listed building (E.1(i)), and an article 4 direction can take Class E away in a defined area.
What the Welsh text does not say
England’s Class E bars houses created by a change of use under Part 3 or a new build under Part 20. The Welsh Class E has no such paragraph, and the check applies no change-of-use test for Wales. A condition on an earlier planning permission can still remove the right, so read your planning history. Flats have no Class E rights anywhere: the definition of “dwellinghouse” in article 1(2) excludes a building containing flats and a flat in one.
The certificate in Wales
A certificate of lawfulness of proposed development is made under section 192 of the 1990 Act, with the procedure in article 28 of the Development Management Procedure (Wales) Order 2012. The council has eight weeks beginning with the day it receives the application, unless you agree a longer period in writing. The application needs the form, a plan identifying the land, and the evidence that verifies the claim.
The fee is half the planning fee. The Welsh Government fee document in force from 1 December 2025 sets £283 for a building in the curtilage of a house (category 7(a)), so the certificate costs £141.50. The Lawful Development Certificate guide walks through the application, and the sample drawings show the sheets a council expects.
Rooms that already exist
If the room is already built, the certificate is one of existing use or development under section 191, and it is not halved: regulation 11(3)(a) of the Welsh fees regulations charges the amount payable for planning permission for the same operations, £283 for a garden room. Section 171B(1)(b) of the 1990 Act sets four years from substantial completion for building operations in Wales, against ten in England, in the text we read on 19 November 2026. legislation.gov.uk also lists a 2026 Act of the Senedd with amendments to section 171B that it has not yet applied, so check the current wording before you rely on it. Dates and evidence are covered in the 4-year and 10-year rules guide.
Building regulations in Wales
Planning permission and building regulations are separate. In Wales the Building Regulations 2010 apply, and Schedule 2 Class 6 exempts a detached single-storey building of up to 15 m² floor area with no sleeping accommodation, and one of 15 m² to 30 m² with no sleeping accommodation if it is at least 1 m from the boundary or built substantially of non-combustible material. Sleeping accommodation or a larger floor area takes the room out of the exemption. The garden room building regulations guide covers the electrics and drainage that still need sign-off.
Scotland and Northern Ireland have their own rules, with different heights and distances: see the guides to Scotland and Northern Ireland.
Sources
Every number in this guide that does not come from our own 3D check was checked against these 9 documents, numbered in the order the text first cites them and read between 11 November 2026 and 19 November 2026. 9 are legislation and government guidance.
- 1legislation.gov.ukThe Town and Country Planning (General Permitted Development) Order 1995, Schedule 2, Part 1, Class E as substituted for Wales by SI 2013/1776 (W.177), revised text
- 2legislation.gov.ukThe Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2013
- 3legislation.gov.ukGPDO 1995, article 1: interpretation, article 1(5) land, height measurement
- 4Welsh GovernmentWelsh Government, planning application fees (fee document from 1 December 2025): category 7(a) £283; certificate for proposed development half (SI 2015/1522, reg. 11)
- 5legislation.gov.ukThe Town and Country Planning (Development Management Procedure) (Wales) Order 2012, articles 5, 10, 11 and 28
- 6legislation.gov.ukTown and Country Planning Act 1990, section 192: certificate of lawfulness of proposed use or development
- 7legislation.gov.ukTown and Country Planning Act 1990, section 191: certificate of lawfulness of existing use or development
- 8legislation.gov.ukTown and Country Planning Act 1990, section 171B: time limits for enforcement (England 10 years for building operations, Wales 4 years), as substituted from 25 April 2024 by the Levelling-up and Regeneration Act 2023, section 115
- 9legislation.gov.ukThe Building Regulations 2010, Schedule 2, Class 6 (small detached buildings), England and Wales